Public Way Impacts

  • Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
  • Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
  • Linden Street and Plympton Street will have a drive lane and both roads will remain open for pedestrians.
  • Linden Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
  • A site fence has been installed, including lighting and signage.
  • Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
  • Continuous deliveries will happen at Linden, Plympton, and Bow Streets.
  • The Tower Crane located in the courtyard will be active from 7:00 AM – 3:00 PM daily.

 Exterior Site Activities

  • Chimney caps, roof slate, and flashing will be installed.
  • Roof decking will be replaced.
  • Regulated materials of the slate roof will be removed at the corner of Bow and Linden Street.
  • Installation of brick veneer will occur.
  • The jack arches and lintels will continue to be rebuilt.
  • Cutting of masonry joints will occur in the courtyard.
  • Dumpster loading with trash chute will continue on Bow Street.
  • Deliveries will be made on Bow Street for load-in of material at southwest gate as well as on Linden Street at the entrance to the Courtyard.

 Interior Site Activities

  • Backfilling of the duct banks will take place.
  • Work will take place at the dormers, including HVAC activities.
  • Framing for vents and joists will take place.
  • Insulation will be installed on the 2nd floor, 3rd floor, and the attic.
  • Layout and top track activities will occur on the 2nd floor east and 3rd floor west.
  • Installation of steel in the Coolidge Room will take place.
  • Windows will be installed.
  • Installation of risers for electrical, plumbing, mechanical, and HVAC will continue, as well as overhead and in-wall rough-ins.