Year: 2022

Week of October 24, 2022

Public Way Impacts Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street. Bow Street will remain closed in front of Randolph Hall from Linden Street to Plympton Street. Plympton Street will have a drive lane and the sidewalk will remain open for pedestrians. Linden Street and Plympton…Continue Reading Week of October 24, 2022

Week of October 24, 2022

Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way, which opened to traffic in July. Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones will be in place. The work will continue into spring 2023 and will be coordinated with University…Continue Reading Week of October 24, 2022

Week of October 17, 2022

Public Way Impacts Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street. Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street. Plympton Street will have a drive lane and the sidewalk will remain open for pedestrians. Linden Street and Plympton Street…Continue Reading Week of October 17, 2022

Week of October 17, 2022

Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way, which opened to traffic in July.  Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones will be in place. The work will continue into spring 2023 and will be coordinated with…Continue Reading Week of October 17, 2022

Week of October 10, 2022

Public Way Impacts The job site will be closed on Monday 10/10 for the holiday and operations will continue on Tuesday 10/11. Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street. Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street. Plympton…Continue Reading Week of October 10, 2022

Week of October 10, 2022

Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way, which opened to traffic in July.  Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones will be in place. The work will continue into spring 2023 and will be coordinated with…Continue Reading Week of October 10, 2022

Allston Development Monthly Update-March 2023

Enterprise Research Campus (ERC)* Phase 1 Enabling Infrastructure WorkEnabling work continues at the parcel of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Much of the project work, which…Continue Reading Allston Development Monthly Update-March 2023

Week of October 3, 2022

Public Way Impacts Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street. Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street. Plympton Street will have a drive lane and the sidewalk will remain open for pedestrians. Linden Street and Plympton Street…Continue Reading Week of October 3, 2022

Week of October 3, 2022

Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way, which opened to traffic in July. Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones will be in place. The work will continue into spring 2023 and will be coordinated with…Continue Reading Week of October 3, 2022

Week of September 26, 2022

Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way, which opened to traffic in July.  Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones will be in place. The work will continue into spring 2023 and will be coordinated with…Continue Reading Week of September 26, 2022