Category: Enterprise Research Campus (ERC) Utility Enabling Work

Week of April 22, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.    As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the HBS…Continue Reading Week of April 22, 2024

Week of April 15, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.   As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of April 15, 2024

Week of April 8, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.     Kresge Way Temporary Relocation As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of April 8, 2024

Week of April 1, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of April 1, 2024

Week of March 25, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of March 25, 2024

Week of March 18, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of March 18, 2024

Week of March 11, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of March 11, 2024

Week of March 4, 2024

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of March 4, 2024

Week of February 26, 2024

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of February 26, 2024

Week of February 19, 2024

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of February 19, 2024