Please note, no work will take place on Monday, May 29th, in observance of Memorial Day.

 

Saturday, May 27, 2017

  • Façade and interior work will continue on the pavilion.
 
 
Site Activities
  • Façade work will continue on the West Pavilion.
  • Exterior brick façade work will continue this week.
  • Rough mechanical piping, metal framing, and dry wall work will take place throughout the week.
  • Stair construction will occur throughout the week.
  • Ceiling and light installations will continue.
  • Painting will continue on the interior.
  • Trucking and deliveries will take place throughout the week.
  • Police details will be onsite to assist with vehicular and pedestrian traffic. 

 

 

 

 

 

 

 

 

 

 

 