Klarman Hall Project Updates

Week of 7/24/17

 

Saturday, July 22, 2017

  • Roof work will continue.
  • Exterior wall framing and sheathing will continue.

 
 
Site Activities 

  • Steel fireproofing is ongoing.
  • Concrete placements and finishes will continue.
  • Masonry work will continue on the interior and exterior.
  • Exterior stud and sheathing work will continue on the South side, as well as along the roof.
  • Roof work will continue.
  • Street drainage work will continue in the Kresge Way Parking Drop-Off area. Detours within the parking area and travel lanes will continue through July.
  • Mechanical systems will begin to be installed within the building.