Project Updates

 

Rotterdam Street Utility Project

Construction Update
11/12/18

 

 

Saturday, November 10, 2018

  • Concrete blocks will be pulled at the Allston Science and Engineering Complex foundation wall.
  • Duct bank work will begin to take place.

 

Site Activities

  • Duct banks work will continue.
  • Sheeting pits will begin to be excavated.