SEC Project Updates

 

 

Construction Update
Week of 1/22/18

 

 

 
Saturday, January 20, 2018

  • Cranes will continue erecting steel above grade.
  • Decking, detailing, and fireproofing will continue to be installed.
  • Tarps will continue to be installed.
  • Snow and water will continue to be cleaned off the decks.
Sunday, January 21, 2018
  • An electrical shutdown to upgrade temporary power will take place.
Site Activities 
  • Cranes will continue erecting steel above grade.
  • Dismantling of the west crane has begun and will be completed next week.
  • Decking, detailing, and fireproofing will continue to be installed.
  • Concrete pours will take place throughout the week.
  • Snow and water removal activities will continue.
  • Tarps will continue to be installed.
  • MEP (mechanical, electrical, and plumbing) installations will continue on the lower levels.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

If you have any construction related questions regarding the Allston Science Project, please email Construction Mitigation at mitigation@csl-consulting.com