Week of 7/23/18
 

Saturday, July 21, 2018

  • Cleaning of the site will continue.
  • Fireproofing will continue to be installed.
  • Steel work within the building will continue.

 

Site Activities

  • Steel work within the building will continue.
  • A large crane will be on site to hoist MEP (mechanical, electrical, and plumbing) equipment onto the roof.
  • Crews will continue placing concrete deck slabs and flood walls.
  • Fireproofing will continue to be installed.
  • MEP’s (mechanical, electrical, and plumbing) installations will continue above and below grade.
  • Erection of the exterior façade will continue.
  • Utility work will continue throughout the site.
  • Materials will continue to be hoisted above grade and loaded through the plaza deck.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 