SEC Project Updates

 

 

Construction Update
Week of 7/24/17

 

 

Saturday, July 22, 2017

  • Demolition activities will continue.
  • Site cleaning will continue.
 
Site Activities 
  • A crane will be erected on the West side of the site this week.
  • Above and below grade steel will continue this week.
  • Demolition activities will continue.
  • Demolition debris will be hauled off site throughout the week.
  • Concrete pours will continue throughout the week.
  • Fireproofing of the below grade steel will continue.
  • Masonry and concrete subcontractors will begin to mobilize.

 

 

 

 

 

 

 

 

 

 

 

 

If you have any construction related questions regarding the Allston Science Project, please email Construction Mitigation at mitigation@csl-consulting.com