SEC Project Updates



Construction Update
Week of 3/19/18

Saturday, March 17, 2018

  • Brackets and sills will begin to be installed.
  • Waterproofing will continue to be installed.
  • Overhead protection will begin to be installed in the shafts.
  • Tarps will continue to be installed.


Site Activities

  • Crews will continue placing concrete deck slabs.
  • Fireproofing will continue to be installed.
  • MEP’s (mechanical, electrical, and plumbing) installations will continue above and below grade.
  • Concrete flood walls will continue to be placed above and below grade.
  • Erection of precast planks at the headhouses will begin to take place.
  • The material hoist will continue to be utilized for deliveries.






























If you have any construction related questions regarding the Allston Science Project, please email Construction Mitigation at