SEC Project Updates

Construction Update
Week of 11/19/18

 

Please note, no work will take place on Thursday, November 22nd in observance of Thanksgiving Day.


Please note, the Rotterdam roadway has been altered to allow northbound only roadway for underground utility line installation. This alteration will remain in place through early January.


Saturday, November 17, 2018

  • Façade work will continue.
  • Interior work will take place.
  • Deliveries to the site will continue.
  • Waterproofing will occur.

Sunday, November 18, 2018

  • Waterproofing will continue.
  • Interior work will take place.

Site Activities 

  • Steel work within the building will continue.
  • Concrete slabs will continue to take place on the deck and within the building.
  • Fireproofing and waterproofing will continue to be installed.
  • MEP’s (mechanical, electrical and plumbing) will continue to be installed.
  • Erection of the exterior façade will continue.
  • Interior stud work will continue.
  • Geofoam will be installed on the plaza deck.
  • Winter weather protection work will begin.
  • Construction materials will be loaded into the site with the use of a hoist.
  • Installation of roofing on the plaza deck will begin.