SEC Project Updates

Construction Update
Week of 8/19/2019

 

Saturday, August 17th 

  • Facade work will continue.
  • Interior work will take place.
  • Waterproofing will occur.
  • Deliveries to the site will continue.

Sunday, August 18th

  • Facade work will continue.
  • Interior work will take place.
  • Waterproofing will occur.
  • Deliveries to the site will continue.

Site Activities

  • Steel and stair work within the building will continue.
  • Fireproofing and waterproofing will continue to be installed.
  • Concrete slabs and hardscaping will continue to take place within the building.
  • MEP’s (mechanical, electrical and plumbing) will continue to be installed.
  • Interior drywall finishes will take place.
  • Floor polishing, bathroom finishes, and installation of tiles and ceiling panels will occur.
  • Erection of glass and the screen facade will continue.
  • The service and passenger elevators will continue to be erected.
  • Installation of concrete panels will continue on the head houses.
  • Landscaping on the plaza deck and terraces will continue.
  • Installation of the roof will continue.
  • Construction materials will be loaded into the site with the use of a service elevator.
  • The Boston Water and Sewer Commissions Western Avenue waterline replacement will occur within construction site limits as night work.

If you have any construction related questions regarding this project, please email Construction Mitigation at mitigation@csl-consulting.com.