SEC Project Updates

Construction Update
Week of 1/14/19


Please note, the Rotterdam roadway has been altered to allow northbound only roadway for underground utility line installation. This alteration will remain in place through mid-February.

 

Saturday, January 12, 2019

  • Façade work will continue.
  • Interior work will take place.
  • Waterproofing will occur.

Site Activities

  • Steel and stair work within the building will continue.
  • Fireproofing and waterproofing will continue to be installed.
  • Concrete slabs will continue to take place on the deck and within the building.
  • MEP’s (mechanical, electrical and plumbing) will continue to be installed.
  • Interior drywall finishes and painting will take place.
  • Erection of the exterior façade will continue.
  • Geofoam will be installed on the plaza deck.
  • Construction materials will be loaded into the site with the use of a hoist.
  • The service elevator will continue to be erected.