Western Avenue Utility Crossing & Roadway Realignment

As part of the enabling work for Harvard's new Science and Engineering Complex (SEC), a section of Western Ave. needed to be realigned to accommdate the installation a new utility tunnel to service the Complex, running across Western Ave from the former Charlesview site to the new SEC project site.

The first phase of the roadway realignment was successfully completed in May 2017 and extends from 130 to 140 Western Ave. The final phase was successfully completed in late February/early March 2020 when the realignment was reversed, returning Western Ave to its original layout.