Western Avenue & SEC Enabling Roadway Projects

As part of the roadway enabling work for Harvard's new Science and Engineering Complex (SEC), a section of Western Ave needed to be realigned to accommodate the installation a new utility tunnel to service the complex, running across Western Ave from the former Charlesview site to the new SEC project site. 

The first phase of the roadway realignment was successfully completed in May 2017 and extends from 130 to 140 Western Ave. The final phase was successfully completed in late February/early March 2020 when the realignment was reversed, returning Western Ave to its original layout. 

The other roadways around the SEC and 114 Western Ave, including Western Ave, Academic Way, Science Drive, Rotterdam Street and Stadium Road, called for new sequencing, paving, and some underground utility work to facilitate the opening of both the SEC, 114 Western Ave, and the new Enterprise Research Campus. These roadways continued to open in phases throughout November/early-December 2020.

Spring 2021 Road Striping Schedule

Beginning on Monday, April 26, and continuing throughout the week, the contractor will be striping and placing pavement markings at and along the following locations:

  • Western Ave from SwissBakers to Soldiers Field Road
  • N. Harvard Street in front of the ArtLab and South Campus Drive
  • The top of South Campus Drive @ N. Harvard Street
  • Academic Way North (Package E – road connecting N. Harvard Street to Western Ave next to the ArtLab)

The work will take place from 7:00 am to 4:00 pm. Police details have been requested to help facilitate this work.

PLEASE NOTE: Traffic flow in these areas may be briefly and occasionally interrupted during this work, however, the roads will be passable and detours not necessary. The same with access to the driveways and roads off of Western Ave.

 

Spring 2021 Paving Schedule

The April 2021 paving schedule and paving locations are as follows. Please note this work is weather dependent so some dates could shift.

Tuesday, April 20 and Thursday, April 22 (7:00 a.m. and 4:00 p.m.)

  • The section of N. Harvard Street in front of the ArtLab and South Campus Drive
  • The top of South Campus Drive @ N. Harvard Street
  • Academic Way North (new road betweem N. Harvard St and Western Ave)

IMPACTS:

  • On N. Harvard Street, the contractor plans to use police details on either end of the work area and alternate traffic using one open lane while they pave the other 2/3 of the roadway. After the 2/3 is paved, two-way traffic will open back up on N Harvard while they finish paving the balance of the road.
  • On Wednesday, April 21, for approximately 4 hours during the paving operation, vehicles will not be able to access South Campus Drive from N Harvard Street.
  • During this time, access to 175 N Harvard’s parking lot will be available by driving behind the Continuum building and the back of 175 N Harvard Street and taking a right off South Campus Drive into the lot.

Thursday, April 22 and Friday, April 23 (7:00 a.m. and 4:00 p.m.)

  • Rena Path Extension
  • SORO Mixed-Use Path Patch Restoration (April 23 only)
  • Rotterdam Street Sidewalk Restoration (April 23 only)

IMPACTS:

  • Access for pedestrians will be maintained on the mixed-use path during this activity.