The following summarizes the work planned on the Adams House Phase 3 renovation for the week of August 21. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Load out from back parking lot and live dumpster loads on Bow Street.
- Historic light fixtures are scheduled to be removed on Tuesday 8/22. A truck will be staged in parking spots on Plympton Street.
EXTERIOR SITE ACTIVITIES:
- Masonry Work on the exterior façade will continue.
- Installation of the man material lift on lower Bow Street will continue.
- Carpentry work on the roof will continue.
- Removal of Iron window grilles will continue.
INTERIOR ACTIVITIES:
- Mechanical, electrical and plumbing make safe and temporary fire alarm/temporary power will continue.
- Temporary protection will continue.
- Abatement will continue inside Westmorly and Russell Hall.
- Interior Demo of Westmorly and Russell Hall.
WORK HOURS:
- Monday to Friday 7am to 3:30pm
- Saturday 8/19 9am to 4:30pm