The following summarizes the work planned on the Adams House Phase 3 renovation for the week of August 28. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Load out from back parking lot and live load of dumpsters on Bow Street.
EXTERIOR SITE ACTIVITIES:
- Masonry Work on the exterior Façade will continue.
- Installation of the man material lift on lower Bow Street will be complete on Tuesday 8/29.
- This lift will become active as soon as installation is complete.
- Carpentry work on the roof will continue.
- Removal of iron window grilles will continue.
INTERIOR ACTIVITIES:
- Temporary Protection will continue.
- Abatement will continue inside Westmorly and Russell Hall.
- Interior demolition of Westmorly and Russell Hall.
WORK HOURS:
- Monday to Friday 7am to 3:30pm and 3:30pm to 10:30pm (No exterior noise after 6pm)
- Saturday 8/26 9am to 4:30pm