The following summarizes the work planned on the Adams House Phase 3 renovation for the week of September 4. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Load out from back parking lot and live load of dumpsters on Bow Street.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Scaffold dismantling on the East Terrace will begin.
- Excavation for access into the basements of Russell and Westmorly.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate until 6:00pm
- Continuing water main work on Bow Street.
INTERIOR ACTIVITIES:
- Temporary protection will continue.
- Abatement will continue inside Westmorly and Russell Hall.
- Interior demolition of Westmorly and Russell Hall.
WORK HOURS:
- Monday 9/4 – Site Closed for Labor Day
- Tuesday to Friday 7:00am to 3:30pm and 3:30pm to 10:30pm (No exterior noise after 6pm)
- Saturday 9/2 – 9:00am to 4:30pm