The following summarizes the work planned on the Adams House Phase 3 renovation for the week of September 18. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Load out from back parking lot and live load of dumpsters on Bow Street will continue.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Excavation for access into the basements of Russell and Westmorly.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate until 6:00pm.
- Roofing abatement at Westmorly will take place.
INTERIOR ACTIVITIES:
- Interior rough carpentry will continue.
- Abatement will continue inside Westmorly and Russell Hall.
- Interior demolition of Westmorly and Russell Hall.
WORK HOURS:
- Monday to Friday: 7:00am to 3:30pm with second shifts from 3:30pm to 10:30pm (No exterior noise after 6pm)
- Saturday 9/23 – 9:00am to 4:30pm