Week of September 18, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of September 18. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Load out from back parking lot and live load of dumpsters on Bow Street will continue.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
  • Excavation for access into the basements of Russell and Westmorly.
  • Man/material hoist will be operating while the site is open.
  • On weekdays the lift will operate until 6:00pm.
  • Roofing abatement at Westmorly will take place.

INTERIOR ACTIVITIES:

  • Interior rough carpentry will continue.
  • Abatement will continue inside Westmorly and Russell Hall.
  • Interior demolition of Westmorly and Russell Hall.

WORK HOURS:

  • Monday to Friday: 7:00am to 3:30pm with second shifts from 3:30pm to 10:30pm (No exterior noise after 6pm)
  • Saturday 9/23 – 9:00am to 4:30pm