The following summarizes the work planned on the Adams House Phase 3 renovation for the week of October 23. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
 - Steel deliveries will begin in the back parking lot. 
- Work from a boom truck is scheduled for the end of the week.
 
 - Eversource is scheduled to remove the existing gas main at the intersection of Bow Street and Arrow Street. 
- This is an Eversource project and is permitted separately from the Adams Phase 3 Project.
 
 
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
 - Scaffolding installation will continue along the south elevation of Westmorly.
 - Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate until 6:00pm.
 
 - Steel will be erected at the roof of Westmorly.
 
INTERIOR ACTIVITIES:
- Interior rough carpentry will continue.
 - Abatement will continue inside Russell Hall.
 - Interior demolition of Westmorly and Russell Hall.
 - Saw cutting and removal of Russell Hall slab will continue.
 - Demolition and excavations at the Conservatory will continue.
 - Temporary heating equipment install will begin next week.
 
WORK HOURS:
- Monday to Friday: 7:00am to 3:30pm with second shifts from 3:30pm to 10:30pm (No exterior noise after 6:00pm)
 - Saturday 10/28 – 9am to 4:30pm