Week of October 23, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of October 23. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  1. Continuous deliveries and dumpster swaps throughout the week.
  2. Steel deliveries will begin in the back parking lot. 
    1. Work from a boom truck is scheduled for the end of the week. 
  3. Eversource is scheduled to remove the existing gas main at the intersection of Bow Street and Arrow Street. 
    1. This is an Eversource project and is permitted separately from the Adams Phase 3 Project. 

EXTERIOR SITE ACTIVITIES:

  1. Masonry work on the exterior façade will continue.
  2. Scaffolding installation will continue along the south elevation of Westmorly.
  3. Man/material hoist will be operating while the site is open.
    1. On weekdays the lift will operate until 6:00pm.
  4. Steel will be erected at the roof of Westmorly.

INTERIOR ACTIVITIES:

  1. Interior rough carpentry will continue.
  2. Abatement will continue inside Russell Hall.
  3. Interior demolition of Westmorly and Russell Hall.
  4. Saw cutting and removal of Russell Hall slab will continue.
  5. Demolition and excavations at the Conservatory will continue.
  6. Temporary heating equipment install will begin next week.

WORK HOURS:

  1. Monday to Friday: 7:00am to 3:30pm with second shifts from 3:30pm to 10:30pm (No exterior noise after 6:00pm)
  2. Saturday 10/28 –  9am to 4:30pm