The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 27. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
- The site fencing and gates along the jersey barriers on Bow Street is scheduled to be replaced.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Masonry cutting work along the west and south elevations.
- Scaffolding installation will continue along north & west elevation of the library.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-5:00pm and Saturday it will operation from 9:00am-4:30pm.
- Dewatering set up will continue at Russell Hall.
- Concrete operations will mobilize.
- Plan concrete deliveries with a pump truck is scheduled for late next week.
INTERIOR ACTIVITIES:
- Interior rough carpentry will continue.
- Interior demolition of Westmorly and Russell Halls.
- Steel erection within Westmorly Hall will continue.
- Saw cutting and removal of Russell Hall slab and Westmorly Hall slab will continue.
WORK HOURS:
- Monday to Friday: 7:00am to 3:30pm
- Saturday 12/2- 9:00am to 4:30pm