The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 12th. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Trucking of soils and concrete will continue next week from Bow Street Gate 2.
- Ongoing deliveries will occur, and concrete pump truck will be within the site fence.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Cutting along the North, West, and South elevations of the project.
- A roofing contractor will continue abatement and demolition of the slate roof on Russell Hall.
- A crane is scheduled to be onsite Tuesday to support this work.
- A crane is scheduled to be inn the back parking lot area for the removal of concrete debris from inside Westmorly Hall.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-3:30pm and Monday/Saturday it will be in operation from 9:00am-4:30pm.
INTERIOR ACTIVITIES:
- Interior wood framing will continue in Westmorly Hall.
- Interior demolition of concrete in Russell Hall.
- Demolition of Westmorly Hall ground level slab will continue.
- Drywall and framing will continue within Westmorly Hall.
- Excavation within Russell Hall basement will continue.
- Excavation for under slab utilities within Westmorly Hall will continue.
- Shoring of existing structure within Westmorly Hall will continue.
- Rebar & concrete work is continuing.
- Mechanical contractors will continue with installation of new HVAC systems within Westmorly Hall.
WORK HOURS:
- Monday to Friday: 7:00am to 3:30pm
- Saturday 2/17 – 9:00am to 4:30pm