Week of February 12, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 12th. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Trucking of soils and concrete will continue next week from Bow Street Gate 2.
  • Ongoing deliveries will occur, and concrete pump truck will be within the site fence.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Cutting along the North, West, and South elevations of the project.  
  • A roofing contractor will continue abatement and demolition of the slate roof on Russell Hall.
    • A crane is scheduled to be onsite Tuesday to support this work.
  • A crane is scheduled to be inn the back parking lot area for the removal of concrete debris from inside Westmorly Hall.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm and Monday/Saturday it will be in operation from 9:00am-4:30pm.

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly Hall.
  • Interior demolition of concrete in Russell Hall.
  • Demolition of Westmorly Hall ground level slab will continue.
  • Drywall and framing will continue within Westmorly Hall.
  • Excavation within Russell Hall basement will continue.
  • Excavation for under slab utilities within Westmorly Hall will continue.
  • Shoring of existing structure within Westmorly Hall will continue.
  • Rebar & concrete work is continuing.
  • Mechanical contractors will continue with installation of new HVAC systems within Westmorly Hall.

WORK HOURS:

  • Monday to Friday: 7:00am to 3:30pm
  • Saturday 2/17 – 9:00am to 4:30pm