The following summarizes the work planned on the Adams House Phase 3 renovation for the week of Marth 4th. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Trucking of soils and concrete will continue next week from Bow Street Gate 2.
- Concrete pump truck is scheduled for next Monday in the rear parking lot.
- There will be no work in the public way on Tuesday, March 5th, due to election polls being open.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Cutting along the East and South of Westmorly Hall.
- A roofing contractor will continue abatement and demolition of slate roof on the Library.
- Scaffolding for Russell Hall chimney re-build will continue.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-3:30pm and Saturday it will be in operation from 9:00am-4:30pm.
INTERIOR ACTIVITIES:
- Interior wood framing will continue in Westmorly Hall.
- Drywall and framing will continue within Westmorly Hall.
- Excavation within Russell Hall’s basement will continue.
- Excavation for under slab utilities within Westmorly Hall will continue.
- Excavations for new footings will continue in Westmorly Hall North.
- Excavations for new Elevator #1 in Westmorly Hall will continue.
- Rebar & concrete work is ongoing.
- A mechanical contractors will continue with installation of new systems within Westmorly Hall.
- Spray foam installation is scheduled for Tuesday.
WORK HOURS:
- Monday to Friday: 7:00am to 3:30pm
- Saturday 3/9 – 9:00am to 4:30pm