The following summarizes the work planned on the Adams House Phase 3 renovation for the week of April 29. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps will occur throughout the week.
- Trucking of soils and concrete will continue from Bow Street Gate 2.
- A crane is scheduled to be on site Monday, April 29 and tentatively on Friday, May 3 to help support the installation of steel in the rear parking lot.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue. Repointing of stone on the North, South & West elevations of Russell Hall and cutting along the West & South elevation of the library commons, and the North & East elevation of Westmorly is progressing. Above the pool theater, within the Westmorly courtyard, cutting and washing activities will take place.
- Abatement and demo of slate roof is expected to wrap up.
- Masonry rebuild for the Russell Hall chimney’s is ongoing.
- Masonry rebuild of the North façade of Westmorly will continue to occur.
- Abatement and stripping continues for the exterior windows of Russell Hall on the South and West elevations.
- On Monday, April 29, a pump truck will be on Bow Street for a concrete placement.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7am-3:30pm and on Saturday it will be in operation from 9am-4:30pm.
INTERIOR ACTIVITIES:
- Interior wood framing and drywall activities will continue to occur in Westmorly.
- Excavations for under slab utilities within Westmorly continues to progress.
- Rebar & concrete work is progressing in Westmorly & Russell Hall.
- Installation of new mechanical systems within Westmorly is ongoing.
- Installation of the elevator shafts within Russell Hall and Westmorly Court will continue.
WORK HOURS:
- Monday to Friday: 7am to 3:30pm
- Saturday, May 4: 9am to 4:30pm