Week of May 6, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 6. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.
  • Trucking of soils and concrete will continue from Bow Street Gate 2.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue. Repointing of stone on the north, south & west elevations of Russell Hall and cutting along the west & south elevation of the library commons, and the north & east elevation of Westmorly is progressing. Above the pool theater, within the Westmorly courtyard, cutting and washing activities will take place.
  • Work on the windows will continue on the south and east elevations of Westmorly.
  • Masonry rebuild for the Russell Hall chimney’s is ongoing.
  • Masonry rebuild of the north façade of Westmorly will continue to occur on the area adjacent to the School of Public Health.
  • Stripping continues for the exterior windows of Russell Hall on the south and west elevations.
  • Mid-week, a pump truck will be on Bow Street for a concrete placement.
  • Man/material hoist will be operating while the site is open.
    1. On weekdays the lift will operate 7am-3:30pm and on Saturday it will be in operation from 9am-4:30pm.

INTERIOR ACTIVITIES:

  • Interior framing and drywall activities will continue to occur in Westmorly.
  • Excavations for under slab utilities within Westmorly continues to progress.
  • Rebar & concrete work will take place in the Conservatory area.
  • Installation of new mechanical systems within Westmorly is ongoing.
  • Installation of the elevator shafts within Russell Hall and Westmorly Court will continue.

WORK HOURS:

  • Monday to Friday: 7am to 3:30pm
  • Saturday, May 11: 9am to 4:30pm