The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 20. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps will occur throughout the week.
EXTERIOR SITE ACTIVITIES:
- Masonry work will continue on the exterior façade of all buildings.
- Masonry rebuilds for the Russell Hall and Westmorly chimney’s is ongoing.
- Masonry rebuild of the window bays at the east elevation of Westmorly is progressing.
- Work activities on the windows will continue to occur at Westmorly.
- Scaffolding continues to be erected on the northeast and east elevations of Russell Hall.
- The erection of the permanent steel structure within Westmorly will continue.
- A concrete truck will be placed inside of the site fence mid-week for a concrete placement.
- Demolition work will occur at the Cupola.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7am-3:30pm and on Saturday it will be in operation from 9am-4:30pm.
INTERIOR ACTIVITIES:
- Interior framing and drywall activities will continue to occur in Westmorly.
- Excavations for under slab utilities within Westmorly continues to progress.
- Installation of new mechanical systems within Westmorly is ongoing.
- Installation of the elevator shafts within Russell Hall and Westmorly continues to take place.
- Steel erection will occur in Russell Hall and Westmorly.
WORK HOURS:
- Please note the site will be closed for Commencement on Thursday, May 23.
- Monday, Tuesday, Wednesday, and Friday: 7am to 3:30pm.
- Saturday, May 25: 9am to 5pm.