Week of May 20, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 20. Please note that items in BOLD are expected to generate some noticeable noise.
 
PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.

EXTERIOR SITE ACTIVITIES:

  • Masonry work will continue on the exterior façade of all buildings.
  • Masonry rebuilds for the Russell Hall and Westmorly chimney’s is ongoing.
  • Masonry rebuild of the window bays at the east elevation of Westmorly is progressing.
  • Work activities on the windows will continue to occur at Westmorly.
  • Scaffolding continues to be erected on the northeast and east elevations of Russell Hall.
  • The erection of the permanent steel structure within Westmorly will continue.  
  • A concrete truck will be placed inside of the site fence mid-week for a concrete placement.
  • Demolition work will occur at the Cupola.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7am-3:30pm and on Saturday it will be in operation from 9am-4:30pm.

INTERIOR ACTIVITIES:

  • Interior framing and drywall activities will continue to occur in Westmorly.
  • Excavations for under slab utilities within Westmorly continues to progress.
  • Installation of new mechanical systems within Westmorly is ongoing.
  • Installation of the elevator shafts within Russell Hall and Westmorly continues to take place.
  • Steel erection will occur in Russell Hall and Westmorly.

WORK HOURS:

  • Please note the site will be closed for Commencement on Thursday, May 23.
  • Monday, Tuesday, Wednesday, and Friday: 7am to 3:30pm.
  • Saturday, May 25: 9am to 5pm.