The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 3. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps will occur throughout the week.
- The project team is coordinating water main disconnections to complete tie-in activities along Bow and Plympton Streets.
EXTERIOR SITE ACTIVITIES:
- Masonry work will continue on the exterior façade of all buildings.
- Masonry rebuilds for the Russell Hall and Westmorly chimneys are ongoing.
- Masonry rebuild of the window bays at the east elevation of Westmorly is progressing.
- Window framing repairs will continue at Westmorly.
- Scaffolding continues to be erected on the northeast and east elevations of Russell Hall.
- The erection of the permanent steel structure within Westmorly is ongoing.
- This activity will require a crane in the back parking lot on Thursday, June 6.
- A pump truck will be placed inside of the site fence for a concrete placement on Wednesday, June 5.
- Demolition work will occur at the Cupola.
- Excavation activities will take plce in the Conservatory Area for utilities and new mechanical tunnels.
- A hoist will be operating while the site is open.
- On weekdays the lift will operate 7am-3:30pm and on Saturday it will be in operation from 9am-4:30pm.
INTERIOR ACTIVITIES:
- Interior framing and drywall activities will occur in Westmorly.
- Excavations for under slab utilities within Westmorly continues.
- Installation of new mechanical systems within Westmorly is ongoing.
- Installation of the elevator shafts within Russell Hall and Westmorly will take place.
- Steel erection will occur in Russell Hall and Westmorly.
- Demolition activities remain ongoing in Russell Hall to support the installation of new steel framing.
WORK HOURS:
- Monday to Friday: 7am to 3:30pm.
- Saturday, June 8: 9am to 4pm.