Week of July 8, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of July 8. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.

EXTERIOR SITE ACTIVITIES:

  • Masonry work will continue to take place on the exterior façade of all buildings.
  • Masonry rebuilds for the Russell Hall and Westmorly chimneys are ongoing.
  • Masonry rebuild of the window bays at the east elevation of Westmorly continues to progress.
  • Window framing repairs remain ongoing at Westmorly.
  • The erection of the permanent steel structure within Russell Hall and Westmorly will continue.  
    • This activity will require the use of a crane on Monday, July 8 and Tuesday, July 9 in the Westmorly north parking lot.
  • A pump truck will be placed inside of the site fence for a concrete placement.
  • Excavation activities will continue to take place in the Conservatory area for utilities and new mechanical tunnels.
  • A hoist will be operating while the site is open.
    • On weekdays the lift will operate 7am-3:30pm. 

INTERIOR ACTIVITIES:

  • Interior framing and drywall activities will continue to occur in Westmorly.
  • Excavations for under slab utilities within Westmorly continue.
  • Installation of new mechanical systems within Westmorly is ongoing.
  • Installation of the elevator shaft in Westmorly Court continues to progress.
  • Steel erection remains ongoing in Russell Hall and Westmorly.
  • Floor prep installation will take place in Russell Hall.
  • Demolition activities continue in Russell Hall to support the installation of new steel framing. 

WORK HOURS:

  • Monday-Friday: 7am to 3:30pm
  • Saturday, July 13: 9am to 4pm