Week of July 15, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of July 15. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue for all buildings.
  • Masonry rebuild for the Russell Hall & Westmorly chimneys will continue.
  • Masonry rebuild of the window bays at the east elevation of Westmorly will continue.
  • Window frame repairs will continue at Westmorly.
  • Erection of the permanent steel structure will continue within Russell Hall and Westmorly.
  • Crane pick scheduled for Monday (7/15), Tuesday (7/16), and Wednesday (7/17) in the Westmorly North Parking Lot
    • Concrete placement scheduled for Monday (7/15) and Thursday (7/18). A pump truck will be within site fence.
  • Excavations for utilities and new mechanical tunnels will continue in the Conservatory Area.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly.
  • Drywall and framing will continue within Westmorly.
  • Excavations for under slab utilities within Westmorly will continue.
  • Mechanical contractors will continue with installation of new systems within Westmorly.
  • Masonry contractor will continue with the install of the elevator shaft in Westmorly Court.
  • Permanent steel erection will continue within Russell Hall and Westmorly.
  • Spray fireproofing will continue within Russell Hall and Westmorly
  • Floor prep install will continue with Russell Hall
  • Steel and concrete demolition will continue within Russell Hall to support new steel framing installation.

WORK HOURS:

  • Monday-Friday (7/15-7/19)- Site open from 7:00am to 3:30pm
  • Saturday (7/20) – Site open from 9:00am to 4:00pm