Week of August 12, 2024

175 North Harvard Street Project Construction Impacts Update

The following is an overview of the work taking place at the 175 North Harvard construction site at the
future location of the new Harvard University affiliate housing building and American Repertory Theatre
(ART):

  • The structural steel phase of the housing project is ongoing rising out of the ground this month.
    Decking will follow through December. Steel beams will be delivered on flat-bed trucks and will be
    offloaded and installed using the tower crane. Concrete decking and detailing will be taking place
    until mid-August. Mechanical, electrical, and plumbing trades are on site working on under slab
    utilities.
  • Bond is installing thermal piping in the Northeast corner of the job site until August 15.
  • The tower crane will be in use into next year during normal working hours and will be placed in
    weathervane mode with safety lighting turned inward at the end of every shift.
  • Wheel washing and street sweeping continues to ensure soil is not being tracked through the
    neighborhood streets.
  • There are no planned road closures on South Campus Drive this week. Only construction vehicles
    are permitted to turn onto South Campus Drive from North Harvard Street for safety reasons and
    to improve traffic flow. All other vehicles are directed to access South Campus Drive from Western
    Ave.
  • On the new American Repertory Theater (ART) work site, crews are excavating for the final
    sequence of foundation and backfill. This foundation work will continue into August. Concrete
    and rebar work will continue through August. Backfilling is ongoing in the substage area.
    Formwork and waterproofing will be ongoing this week. Tie-ins for the mat slab work take place
    this week.
  • Building mock-ups to review design and constructability are underway across North Harvard
    Street. The curtain wall for the mock-up will be delivered in late August/early September.
  • Because of the weather, the affiliate housing building crew may work on site this Saturday, August
  • They do have plans to work on Saturday, August 17, to progress with structural steel and
    decking work.
  • The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and
    Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.