Dates 9/23/24 to 9/28/24:
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps will occur throughout the week.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue to take place for all buildings.
- Roofing installation will take place on the Westmorly and Russell Hall roofs.
- New copper cladding will continue preparation at the Russell Hall Tower.
- Window frame repairs will remain ongoing at Westmorly & Russell Hall.
- Adjustment of Russell Hall Balustrade scaffold will continue next week.
- Library scaffolding will continue to be dismantled next week.
- A hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-3:30pm
INTERIOR ACTIVITIES:
- Framing and drywall will continue to progress within Westmorly & Russell Hall.
- The installation of new systems will continue within Westmorly & Russell Hall.
- Permanent steel erection is progressing within Russell Hall and Westmorly.
- Spray foam insulation will continue within Westmorly & Russell Hall.
SCHOOL OF PUBLIC HEALTH IMPACTS:
- Masonry work continues adjacent to 9 Bow St and 22 Plympton St.
- Material for masonry and carpentry work will load in via Rear Lot.
- Spray foam insulation truck will be parked within site fence to facilitate spray foam insulation within Westmorly.
WORK HOURS:
- Monday-Friday 7:00am to 3:30pm
- Saturday, September 28 9:00am to 4:00pm