Week of October 7, 2024

Dates 10/7/24 to 10/12/24:
 
PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue to take place for all buildings.
  • Roofing installation will take place on the Westmorly and Russell Hall roofs.
  • New copper cladding will continue preparation at the Russell Hall Tower.
  • Concrete placement scheduled for Friday, October 11. A pump truck will be within the site fence.  
  • Window frame repairs will remain ongoing at Westmorly & Russell Hall.
  • A hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm

INTERIOR ACTIVITIES:

  • Framing and drywall will continue within Westmorly & Russell Hall.
  • The installation of new systems will continue within Westmorly & Russell Hall.
  • Permanent steel erection is progressing within Russell Hall and Westmorly.
  • Spray foam insulation will continue within Westmorly.

SCHOOL OF PUBLIC HEALTH IMPACTS:

  • Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
  • Material for masonry and carpentry work will load in via Rear Lot.

WORK HOURS:

  • Monday-Friday 7:00am to 3:30pm
  • Saturday, October 12 – Site Open from 9:00am to 4:00pm