Week of October 14, 2024

Dates 10/15/24 to 10/19/24:

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.
  • Water Service work will continue next week. Water shutdown has been coordinated with the City of Cambridge for the night of Thursday, October 17 into Friday, October 18 starting at midnight until 6:00 AM.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue to take place for all buildings.
  • There will be a crane onsite to remove roofing material on Saturday October 12. The crane will be located in the 22 Plympton Street parking lot.
  • Roof installation will take place on the Westmorly and Russell Hall roofs.
  • New copper cladding installation will continue at the Russell Hall Tower.
  • Concrete placement scheduled for Wednesday, October 16. A pump truck will be within the site fence.
  • A crane will be onsite on Tuesday, October 15 to hoist steel into Russell Hall. The crane will be within the site fence.
  • Window frame repairs remain ongoing at Westmorly & Russell Hall.
  • A hoist will be operating while the site is open.
  • On weekdays the lift will operate 7:00am-3:30pm

INTERIOR ACTIVITIES:

  • Framing and drywall will continue within Westmorly & Russell Hall.
  • The installation of new systems will continue within Westmorly & Russell Hall.
  • Permanent steel erection is progressing within Russell Hall.
  • Spray foam insulation will continue within Westmorly.

SCHOOL OF PUBLIC HEALTH IMPACTS:

  • Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
  • Material for masonry and carpentry work will load in via Rear Lot.
  • Spray foam insulation truck will be parked within the site fence to facilitate spray foam insulation within Westmorly.

WORK HOURS:

  • Tuesday-Friday 7:00am to 3:30pm
  • Job Site will be closed on Monday, October 14.
  • Saturday, October 19 – Site Open from 9:00am to 4:00pm