Week of October 14, 2024

The following summarizes the utility work planned in the Littauer Lot for the week of October 14. Please note that items in BOLD are expected to generate some noticeable noise.
 
Dates: 10/15/24-10/18/24
 
PUBLIC WAY IMPACTS:

  • The construction of temporary access for site entry will continue off of Massachusetts Ave. A portion of the sidewalk to the west of Littauer will be closed and a pedestrian detour will be marked.
  • Construction of temporary turnaround will continue. No parking areas will be coned off on the east end of Littauer lawn. 
  • Detours will be marked on pedestrian walkways that will be closed due to test pit work.  

EXTERIOR SITE ACTIVITIES:

  • Construction and paving of temporary construction access is underway.
  • Construction and paving of temporary turnaround will begin.
  • A vacuum excavation truck will be on site Thursday, October 17 and Friday, October 18 to perform test pits from 7:00 AM – 3:00 PM.

OTHER IMPACTS:

  • No other impacts are expected.

WORK HOURS:

  • Tuesday- Friday 7:00 AM to 3:30 PM. 
  • Job site will be closed on Monday, October 14 
  • No work is planned for Saturday, October 19.