Week of November 4, 2024

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.
  • There will be a crane onsite that will require Bow & Arrow Streets to be closed on Saturday, November 2 beginning at 12AM to Sunday, November 3 at 5AM. Police details, road closures, and noise variance permits have been coordinated with the City of Cambridge. As such, the initial crane pick may start at approximately 6:00am.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue for all buildings.
  • Roofing installation will take place on the Russell Hall & Library Commons roofs.
  • New copper cladding installation will continue at the Russell Hall Tower.
  • Window frame repairs remain ongoing at Westmorly & Russell Hall.
  • A hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm

INTERIOR ACTIVITIES:

  • Framing and drywall will continue within Westmorly & Russell Hall.
  • The installation of new systems will continue within Westmorly & Russell Hall.
  • Spray foam insulation will continue within Westmorly.

SCHOOL OF PUBLIC HEALTH IMPACTS:

  • Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
  • Masonry and carpentry work will load in via Rear Lot.

 WORK HOURS:

  • Monday-Friday 7:00am to 3:30pm
  • Saturday, November 9 – Site Open from 9:00am to 4:00pm