The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 11. Please note that items in BOLD are expected to generate some noticeable noise.
Dates 11/11/24 – 11/09/24
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps will occur throughout the week.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue for all buildings.
- Roofing installation will continue on the Russell Hall & Library Commons roofs.
- New copper cladding installation is ongoing at the Russell Hall Tower.
- Window frame repairs remain ongoing at Westmorly & Russell Hall.
- Scaffold dismantle will begin at Russell Hall.
- A hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-3:30pm
INTERIOR ACTIVITIES:
- Framing and drywall will continue within Westmorly & Russell Hall.
- The installation of new systems will continue within Westmorly & Russell Hall.
- Spray foam insulation will continue within Westmorly.
SCHOOL OF PUBLIC HEALTH IMPACTS:
- Masonry work will continue adjacent to 9 Bow and 22 Plympton Street.
- Masonry and carpentry material will load via Rear Lot.
- Spray foam insulation truck will be parked within the site fence to facilitate spray foam insulation within Westmorly. (Tuesday-Friday)
WORK HOURS:
- Tuesday-Friday 7:00am to 3:30pm
- Job Site will be closed on Monday, November 11 for Veterans Day
- Saturday, November 16 – Site Open from 9:00am to 4:00pm