Week of November 11, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 11. Please note that items in BOLD are expected to generate some noticeable noise.

Dates 11/11/24 – 11/09/24

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue for all buildings.
  • Roofing installation will continue on the Russell Hall & Library Commons roofs.
  • New copper cladding installation is ongoing at the Russell Hall Tower.
  • Window frame repairs remain ongoing at Westmorly & Russell Hall.
  • Scaffold dismantle will begin at Russell Hall.
  • A hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm

INTERIOR ACTIVITIES:

  • Framing and drywall will continue within Westmorly & Russell Hall.
  • The installation of new systems will continue within Westmorly & Russell Hall.
  • Spray foam insulation will continue within Westmorly.

SCHOOL OF PUBLIC HEALTH IMPACTS:

  • Masonry work will continue adjacent to 9 Bow and 22 Plympton Street.
  • Masonry and carpentry material will load via Rear Lot.
  • Spray foam insulation truck will be parked within the site fence to facilitate spray foam insulation within Westmorly. (Tuesday-Friday)

WORK HOURS:

  • Tuesday-Friday 7:00am to 3:30pm
  • Job Site will be closed on Monday, November 11 for Veterans Day
  • Saturday, November 16 – Site Open from 9:00am to 4:00pm