The following summarizes the utility work planned in the Littauer Lot for the week of November 18. Please note that items in BOLD are expected to generate some noticeable noise.
Dates: 11/18/24-11/22/24
PUBLIC WAY IMPACTS:
- Fencing will be extended to the area of Littauer tie-in.
- Fencing will remain in place in front of Austin Hall with Pedestrian Detours marked. The walkway between Austin Hall and Hemenway Gymnasium will be opened for access.
EXTERIOR SITE ACTIVITIES:
- Formwork and reinforcing installation for walls will occur within the site fence.
- Duct bank excavation will continue within the site fence.
- Conduit installation will continue.
OTHER IMPACTS:
- No other impacts are expected.
WORK HOURS:
- Monday-Friday 7:00 AM to 3:30 PM.