Week of December 2, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 2. Please note that items in BOLD are expected to generate some noticeable noise.

Dates 12/2/24 to 12/7/24: 
 
PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue to occur for all buildings.
  • Roofing installation will continue on the Russell Hall & Library Commons roofs.
  • Installation of new copper cladding is ongoing at the Russell Hall Tower.
  • Window frame repairs will continue at Westmorly & Russell Hall.
  • Wood framing will continue at Westmorly Pool Theater Roof.
  • Scaffold dismantle will continue at Russell Hall.
  • A hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm

INTERIOR ACTIVITIES:

  • Framing and drywall will continue within Westmorly & Russell Hall.
  • Installation of new systems will continue within Westmorly & Russell Hall.
  • Spray foam insulation will continue within Westmorly.

SCHOOL OF PUBLIC HEALTH IMPACTS:

  • Masonry work will continue adjacent to 9 Bow and 22 Plympton Street.
  • Material loading for masonry and carpentry work via Rear Lot.

 WORK HOURS:

  • Monday-Friday 7:00am to 3:30pm
  • Saturday, December 7 – Site Open from 9:00am to 4:00pm