Week of December 2, 2024

The following summarizes the utility work planned in the Littauer Lot for the week of December 2. Please note that items in BOLD are expected to generate some noticeable noise.

Dates: 12/2/24-12/7/24

PUBLIC WAY IMPACTS:

  • Fencing will remain in place in the area of the Littauer tie-in.
  • Fencing to west and south of Austin Hall will be relocated to Phase 2A which will extend the work zone to the Littauer Entrance. Entrance will remain open with pedestrian detours marked. This activity is planned for Wednesday, December 4. This activity is planned for Wednesday, December 4. Please note this work is taking place a little sooner than proposed on the original schedule.

EXTERIOR SITE ACTIVITIES: 

  • Waterproofing will be installed. Backfilling and excavation will occur within the site fence. Noise and vibration impact for backfilling.
  • New drain manhole will be installed in area of Littauer tie-In. Noise and vibration impact for backfilling around new manhole and installing a new pipe.
  • Electrical conduit will be installed towards Littauer Tie-In.
  • Excavation will begin for duct bank from Littauer tie-in towards the Littauer entrance. Noise impact for cutting of asphalt for excavation. 

OTHER IMPACTS:

  • Coring for tie-in at Littauer on Monday, December 2. Noise impact for drilling and coring.

WORK HOURS:

  • Monday – Friday 7:00 AM to 3:30 PM. 
  • No work is planned for Saturday, December 7.