The following summarizes the utility work planned in the Littauer Lot for the week of December 9. Please note that items in BOLD are expected to generate some noticeable noise.
Dates: 12/9/24-12/13/24
PUBLIC WAY IMPACTS:
- Fencing will remain in place for Phase 2A.
EXTERIOR SITE ACTIVITIES:
- Backfilling and removal of support of excavation will continue within the site fence. Noise and vibration impact during backfilling.
- Electrical conduit will be installed to connect duct banks to the manhole and extend the duct bank to Littauer tie-in.
- Concrete placement for the duct bank to Littauer tie-in will occur within the site fence.
- Excavation will occur for the duct bank tie-ins to the new temporary transformer location. Noise impact during cutting of asphalt where the duct banks cross walkways.
- Excavation will continue for the duct bank from Littauer tie-in towards Littauer entrance including excavation for a new catch basin near Littauer entrance. Noise impact when cutting asphalt for excavation.
- On Tuesday, December 10 saw cutting asphalt in various locations will occur. The work will be from 7:00 AM – 3:00 PM on and off throughout the day. The areas that are not behind the fencing will have work zones coned off; cones will be moved as the work shifts.
OTHER IMPACTS:
- No other impacts are expected.
WORK HOURS:
- Monday-Friday 7:00 AM to 3:30 PM.
- Work is pending on Saturday, December 14.