The following summarizes the utility work planned in the Littauer Lot for the week of December 16. Please note that items in BOLD are expected to generate some noticeable noise.
Dates: 12/16/24-12/20/24
PUBLIC WAY IMPACTS:
- Fencing will remain in place for Phase 2A
EXTERIOR SITE ACTIVITIES:
- Backfilling and paving will take place within the site fence. Noise and vibration impact for backfilling and paving operation.
- Backfilling and paving will take place at the Littauer tie-in. Noise and vibration impact for backfilling and paving operation.
- Excavation for the duct bank will continue from Littauer tie-in towards Littauer entrance including excavation for new catch basin in area of Littauer entrance. Noise impact excavation operation.
- A catch basin in the area of Littauer entrance will be installed. Noise and vibration impact for backfilling operation.
OTHER IMPACTS:
- No other impacts are expected
WORK HOURS:
- Monday-Friday 7:00 AM to 3:30 PM.
- Tentative plan to work Saturday, December 21 if any days are lost during the week due to weather.