Week of December 23, 2024

Please note the work site will be open on Saturday, December 21 from 9:00 AM to 4:00 PM. Backfilling the duct bank that was placed this week within the site fence. Noise and vibration impact for the backfilling operation.

The following summarizes the utility work planned in the Littauer Lot for the week of December 23 Please note that items in BOLD are expected to generate some noticeable noise.

Dates: 12/23/24-12/27/24

PUBLIC WAY IMPACTS:

  • Fencing will relocate to Phase 2B/2C. 

EXTERIOR SITE ACTIVITIES:

  • Backfilling and paving will take place within the site fence. Noise and vibration impact for backfilling and paving operation. 
  • Backfilling and paving will take place at the Littauer curb line. Noise and vibration impact for backfilling and paving operation.  
  • Conduit will be installed at the Littauer tie-in and continue to the Littauer entrance. 
  • Installation for the catch basin around the Littauer entrance will continue. Noise and vibration impact for backfilling operation.
  • Excavation will begin from the Littauer entrance. Noise impact from excavation operation.

OTHER IMPACTS:

  • Possible concrete placement towards the end of week at Littauer tie-in.
  • A 40-foot trailer for the Science Center Teaching Labs Renovation Project is arriving on Friday, December 27 and will be temporarily placed between the Science Center and the Music Building until Wednesday, January 8.

WORK HOURS:

  • Monday-Tuesday and Thursday -Friday 7:00 AM to 3:30 PM.
  • The site will be closed on Wednesday, December 25 for the Christmas Holiday.  
  • Tentative plan to work Saturday, December 28 if any days are lost during the week due to weather.