The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 30. Please note that items in BOLD are expected to generate some noticeable noise.
Dates 12/30/24 to 1/4/25:
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps will occur throughout the week.
- Removal of an overhead electrical wire to the telephone pole adjacent to 22 Plympton Street is scheduled to be removed. Awaiting confirmation from Eversource on the exact date and time. SDC doesn’t expect any interruptions for access to the 22 Plympton St Lot during this removal.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue for all buildings.
- Roofing installation will continue on the Russell Hall & Library Commons roofs.
- Installation of new copper cladding will continue at the Russell Hall tower.
- Window frame repairs remain ongoing at Westmorly & Russell Hall.
- Wood framing will continue on the Westmorly Pool Theater roof.
- Steel delivery for Westmorly stairway to roof scheduled for Monday, December 30. This is within the site fence.
- Mechanical work continues on the Westmorly roof.
- A hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-3:30pm
INTERIOR ACTIVITIES:
- Framing and drywall will continue within Westmorly & Russell Hall.
- Installation of new systems will continue within Westmorly & Russell Hall.
- Spray foam insulation will continue within Westmorly & Russell Hall.
- Floor prep & tile installation will continue within Westmorly.
- Millwork installation will continue within Westmorly.
- Hardwood flooring is scheduled to mobilize to the site.
- Installation of steel stairways to the roof will occur.
SCHOOL OF PUBLIC HEALTH IMPACTS:
- Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
- Masonry and carpentry material will load in via Rear Lot.
WORK HOURS:
- Monday, Tuesday, Thursday, & Friday 7:00am to 3:30pm.
- Job Site will be closed on Wednesday, January 1 for New Years Day.
- Saturday, January 4 – Site Open from 9:00am to 4:00pm. This work is TBD depending on Sub-contractor availability.