The following summarizes the utility work planned in the Littauer Lot for the week of January 13 Please note that items in BOLD are expected to generate some noticeable noise.
Dates: 1/13/25-1/17/25
PUBLIC WAY IMPACTS:
- Fencing will remain relocated in Phase 2B/2C with Bulletin 2 work.
EXTERIOR SITE ACTIVITIES:
- Excavation will continue from the Littauer Entrance towards the manhole. Noise impact from excavation operation.
- Excavation and backfill will continue for temporary transformer duct banks and pad in front of Austin Hall. Noise and vibration impact from excavation and backfilling operations.
- Backfill and restoration will begin from the Littauer Tie-In area towards the Littauer Entrance. Noise and vibration impact from backfilling and paving operations.
- Conduit installation will begin from the Littauer Entrance towards the manhole.
OTHER IMPACTS:
- Concrete placements at Temporary Transformer Area and in front of Littauer.
WORK HOURS:
- Monday-Friday 7:00 AM to 3:30 PM.
- Tentative plan to work Saturday, January 18 from 9:00 AM to 4:00 PM to maintain schedule.