The following summarizes the utility work planned in the Littauer Lot for the week of January 20 Please note that items in BOLD are expected to generate some noticeable noise.
Dates: 1/20/25-1/24/25
PUBLIC WAY IMPACTS:
- Fencing will remain relocated in Phase 2B/2C with Bulletin 2 Work. The fencing around the Littauer Tie-In will be removed once the restoration of this area is complete.
EXTERIOR SITE ACTIVITIES:
- Backfill and restoration will continue from the Littauer Entrance area towards the manhole. Noise and vibration impact from backfilling and paving operations.
- Backfill and grading for the temporary transformer pad in front of Austin Hall will continue. Noise and vibration impact from backfilling operation.
- Excavation for the 4×6 manhole will begin in front of Littauer. Noise impact from excavation operation.
OTHER IMPACTS:
- A vacuum Truck will be on site Monday, January 20 to perform test pit excavation in front of Paine Hall. Paving of the test pit area is scheduled to occur on Tuesday, January 21. Noise impacts from the Vacuum Truck. Vibration impacts from backfill and paving operations.
WORK HOURS:
- Monday-Friday 7:00 AM to 3:30 PM.
- Tentative plan to work Saturday, January 25 from 9:00 AM to 4:00 PM to maintain schedule.