Week of January 27, 2025

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 27. Please note that items in BOLD are expected to generate some noticeable noise.

Dates 1/27/25 to 2/01/25:

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue for all buildings.
  • Roofing installation will continue on the Russell Hall & Library Commons roofs.
  • Installation of new copper cladding will continue at the Russell Hall Tower.
  • Window frame repairs will continue at Westmorly & Russell Hall.
  • Wood framing will continue on the Westmorly Pool Theater roof.
  • Mechanical work continues on the Westmorly roof.
  • Scaffolding dismantle will continue at Westmorly & Russell Hall.
  • The hoist will be dismantled starting on Monday, January 27. A Crane will be onsite Wednesday, January 29 to facilitate the dismantle. The crane will be within the site fence.

INTERIOR ACTIVITIES:

  • Framing and drywall will continue within Westmorly & Russell Hall.
  • Installation of new systems will continue within Westmorly & Russell Hall.
  • Spray foam insulation will continue within Westmorly & Russell Hall.
  • Floor prep & tile installation will continue within Westmorly.
  • Millwork installation will continue within Westmorly.
  • Hardwood flooring installation will continue within Westmorly.
  • Elevators will begin to be installed within Westmorly.
  • Installation of steel stairways will continue.

SCHOOL OF PUBLIC HEALTH IMPACTS:

  • Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
  • Masonry and carpentry material work will load in via Rear Lot.
  • Excavation for a grease tank in the 22 Plympton Street Lot will continue. A crane will be onsite next week to install the tank. Date TBD.

WORK HOURS:

  • Monday-Friday 7:00am to 3:30pm.
  • Saturday February 1, 2025 – Site Open from 9:00am to 4:00pm