Week of January 27, 2025

 Consigli/Bond are now planning to work on Saturday, January 25 from 9:00 AM to 4:00 PM.

Dates: 1/27/25-1/31/25

PUBLIC WAY IMPACTS:

  • Fencing will be re-located to Phase 3A after paving is complete in Phase 2B/2C. Fence at area of new manhole will remain in place.
  • Harvard University Police will have a detail present to help direct both pedestrian and vehicle traffic.

EXTERIOR SITE ACTIVITIES: 

  • Backfill and restoration will continue from the Littauer Entrance area towards the manhole. Noise and vibration impact from backfilling and paving operations. 
  • Backfill and grading for the temporary transformer pad in front of Austin Hall will continue. Noise and vibration impact from backfilling operation.
  • Excavation for a duct bank will begin. Noise impact from excavation operation.
  • Excavation for the 4×6 manhole will continue in front of Littauer. Noise impact from excavation operation.

OTHER IMPACTS:

  • No other impacts are expected.

WORK HOURS:

  • Monday-Friday 7:00 AM to 3:30 PM.  
  • Tentative plan to work Saturday, February 1 if needed to maintain schedule.