Week of February 3, 2025

Dates: 2/3/25-2/8/25

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.
  • Plympton Street may be closed to vehicles at times during regular work hours to facilitate work in and around the parking lot at 22 Plympton Street. Abutters will be notified.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue for all buildings.
  • Roofing installation will continue on the Russell Hall & Library Commons roofs.
  • Window frame repairs will continue at Westmorly & Russell Hall.
  • Wood framing will continue on the Westmorly Pool Theater roof.
  • Mechanical work continues on the Westmorly roof.
  • Scaffolding dismantle will continue at Westmorly & Russell Hall.

INTERIOR ACTIVITIES:

  • Framing and drywall will continue within Westmorly & Russell Hall.
  • Installation of new systems will continue within Westmorly & Russell Hall.
  • Spray foam insulation will continue within Westmorly & Russell Hall.
  • Floor prep & tile installation will continue within Westmorly.
  • Millwork installation will continue within Westmorly.
  • Hardwood flooring installation will continue within Westmorly.
  • Elevators will begin to be installed within Westmorly.

SCHOOL OF PUBLIC HEALTH IMPACTS:

  • Excavation for utilities in the 22 Plympton Street Lot will continue.
  • Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
  • Masonry and carpentry material work will load in via Rear Lot.

WORK HOURS:

  • Monday-Friday 7:00am to 3:30pm.
  • Saturday February 8, 2025 – Site Open from 9:00am to 4:00pm