The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 10. Please note that items in BOLD are expected to generate some noticeable noise.
Dates: 2/18/25-2/22/25
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps will occur throughout the week.
- Plympton Street will be closed to vehicles at times during regular work hours to facilitate work in and around the parking lot at 22 Plympton Street for the work associated with the new grease tank for the Adams Phase 3 kitchen renovations. Abutters will be notified.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue for all buildings.
- Masonry work will begin on the East Terrace outside of Westmorly Hall.
- Roofing installation will continue on the Dining Hall & Library Commons roofs.
- Window frame repairs will continue at Westmorly & Russell Hall.
- Mechanical work continues on the Westmorly roof.
- Scaffolding dismantle will continue at Westmorly & Russell Hall.
INTERIOR ACTIVITIES:
- Framing and drywall will continue within Westmorly & Russell Hall.
- The installation of new systems will continue within Westmorly & Russell Hall.
- Spray foam insulation will continue within Westmorly & Russell Hall.
- Floor prep & tile installation will continue within Westmorly.
- Millwork installation will continue within Westmorly.
- Hardwood flooring installation will continue within Westmorly.
- Elevators will continue to be installed within Westmorly and Russell Hall.
SCHOOL OF PUBLIC HEALTH IMPACTS:
- Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
- Masonry and carpentry material will load in via Rear Lot.
- Excavation for utilities at 22 Plympton Street Lot will continue.
WORK HOURS:
- Tuesday-Friday 7:00am to 3:30pm.
- Site is closed on Monday, February 17 for Presidents Day.
- Saturday, February 22– Site Open from 9:00am to 4:00pm