The following summarizes the utility work planned in the Littauer Lot for the week of February 24. Please note that items in BOLD are expected to generate some noticeable noise
Dates: 2/24/25-2/28/25
PUBLIC WAY IMPACTS:
- Fencing will remain in place for Phase 3B and pedestrian traffic will be detoured as needed on Holmes Walk.
- Fencing will be downsizing to create additional parking in the Littauer Lot on Friday.
EXTERIOR SITE ACTIVITIES:
- Backfill of trench from new pre-cast manhole at the east end of Littauer towards the existing manhole adjacent to Paine Hall will continue. Noise and vibration impact from backfill operation.
- Paving of trench from new pre-cast manhole at east end of Littauer towards the existing manhole adjacent to Paine Hall will begin. Noise and vibration impact from paving operation.
OTHER IMPACTS:
- No other impacts are expected.
WORK HOURS:
- Monday-Friday 7:00 AM to 3:30 PM.
- No plan to work on Saturday, March 1 at this time.