The following summarizes the utility work planned in the Littauer Lot for the week of March 3. Please note that items in BOLD are expected to generate some noticeable noise
Dates: 3/3/25-3/7/25
PUBLIC WAY IMPACTS:
- The work zone will be established at the Jefferson turnaround area. Vehicle parking for occupied spots will be available in the Littauer Lot outside of the laydown yard.
- Please inform contractors there is no parking allowed at the Littauer Lot turnaround area.
EXTERIOR SITE ACTIVITIES:
- Stripping of topsoil from the Jefferson turnaround area will begin. Noise impact from excavation operation.
- Excavation and preparation for subbase at the Jefferson turnaround area will begin. Noise and vibration impact from compaction operation.
OTHER IMPACTS:
- All excess soil from Jefferson turnaround area will be brought to the Littauer turnaround area.
WORK HOURS:
- Monday-Friday 7:00 AM to 3:30 PM.
- No plan to work Saturday, March 8 at this time.