The following summarizes the work planned on the Adams House Phase 3 renovation for the week of April 22. Please note that items in BOLD are expected to generate some noticeable noise.

Dates: 4/22/25-04/26/25
 
PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.
  • A water service tie-in within the site fence is scheduled for the night of Tuesday April 22nd from 11PM to 7AM. Abutters have been notified.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue for all buildings.
  • Masonry and landscaping work will continue on the East Terrace outside of Westmorly Hall.
  • Excavation, concrete, and masonry work will continue on the South Elevation outside of Westmorly Hall.
  • Roofing installation is ongoing on the Dining Hall & Library Commons roofs.
  • Window brickmold installation and painting at Westmorly & Russell Hall.
  • Mechanical work continues on the Westmorly roof.
  • Scaffolding dismantle will continue at Westmorly & Russell Hall.

INTERIOR ACTIVITIES:

  • Framing and drywall will continue within Westmorly & Russell Hall.
  • Installation of new systems will continue within Westmorly & Russell Hall.
  • Spray foam insulation will continue within Westmorly & Russell Hall.
  • Floor prep & tile installation will continue within Westmorly.
  • Millwork installation will continue within Westmorly.
  • Hardwood flooring installation will continue within Westmorly.
  • Elevators will continue to be installed within Westmorly and Russell Hall.

SCHOOL OF PUBLIC HEALTH IMPACTS:

  • Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
  • Scaffolding dismantle will be completed on Wednesday in the North parking lot.
  • Excavation and paving prep work will begin in the North parking lot.

WORK HOURS:

  • Tuesday-Friday 7:00am to 3:30pm.
  • The job site is closed on Monday, April 21 for Patriot’s Day.