Week of May 5, 2025

The following summarizes the work planned at 12 Palmer St for the week of May 5. Please note that items in BOLD are expected to generate some noticeable noise. 

Dates: 5/05/25 – 5/10/25

Public Way Impacts:

• Short-term scaffolding delivery will be on Monday, May 5.  

• No major road closures are anticipated.

Exterior Site Activities:

• Masons will be working on the exterior masonry demolition on the scaffolding. This will involve cutting and chipping of the brick.

Interior Activities:

• Thursday, May 8 crews will be conducting an emergency evacuation drill where they will be using an air horn 3 times.

Miscellaneous chipping and demolition in the penthouse of the building.

Other Impacts:

• No other impacts are expected.

Work Hours:

• Monday-Friday 7:00 AM to 3:30 PM.

• No plan to work Saturday, May 10 at this time.