The following summarizes the utility work planned in the Littauer Lot for the week of May 12. Please note that items in BOLD are expected to generate some noticeable noise
Dates: 5/12/25-5/16/25
PUBLIC WAY IMPACTS:
- Work zones will be coned off at the manhole located outside of Austin Hall to allow work inside the manhole.
- Additional cones and signage will be installed for the Groundbreaking Ceremony, these will stay in place until after Commencement.
EXTERIOR SITE ACTIVITIES:
- McDonald Electric will be working inside the manhole located outside of Austin Hall installing equipment and wiring. There will be minimal noise impacts from this operation.
- The office trailer will be removed from the site on Tuesday, May 13. There will be minimal noise impacts from this operation.
- A loader and dump truck will be on site starting Thursday, May 15 to set up for the groundbreaking ceremony. There will be noise impacts from this operation.
OTHER IMPACTS:
- For your awareness, a groundbreaking ceremony will occur on Friday, May 16.
WORK HOURS:
- Monday-Friday 7:00 AM to 3:30 PM.
- No plan to work Saturday, May 17 at this time.