The following summarizes the work planned at 12 Palmer St for the week of May 27. Please note that items in BOLD are expected to generate some noticeable impacts.
Dates: 5/27/25-5/30/25Public Way Impacts:
- Palmer St will be closed on Friday May 30 from 7:00am-3:30pm for a crane pick. Bank of America parking spots will be needed for this work to be completed.
- Delivery on Wednesday, May 28 will temporarily block Palmer St. Crews will coordinate with any other activities on the street.
Exterior Site Activities:
- Masonry demolition continues on the scaffolding. This will involve cutting and chipping of the brick. There will be noise impacts from this operation. There will be no masonry demolition on Thursday, May 29.
Interior Activities:
- Sawcutting concrete slabs will continue this week on level 1. There will be no saw cutting on Thursday, May 29.
Other Impacts:
- Thursday, May 29 is Harvard Commencement. The job site will be open but only working on non-impactful activities inside the building.
Work Hours:
- Monday-Friday 7:00 AM to 3:30 PM.
- No plan to work Saturday, May 30 at this time.